e. A, the owner of a boat, contracts with B to take a cargo of jute to Mirzapur, for sale at that place, starting on a specified day. The boat, owing to some avoidable cause, does not start at the time appointed, whereby the arrival of the cargo at Mirzapur is delayed beyond the time when it would have arrived if the boat had sailed according to the contract. After that date, and before the arrival of the cargo, the price of jute falls. The measure of the compensation payable to B by A is the difference between the price which B could have obtained for the cargo at Mirzapur at the time when it would have arrived if forwarded in due course, and its market price at the time when it actually arrived.
f. A contracts to repair B's house in a certain manner, and receives payment in advance. A repairs the house, but not according to contract. B is entitled to recover from A the cost of making the repairs conform to the contract.
g. A contracts to let his ship to B for a year, from the first of January, for a certain price. Freights rise, and, on the first of January, the hire obtainable for the ship is higher than the contract price. A breaks his promise. He must pay to B, by way of compensation,a sum equal to the difference between the contract price and the price for which B could hire a similar ship for a year on and from the first of January.
h. A contracts to supply B with a certain quantity of iron at a fixed price, being a higher price than that for which A could procure and deliver the iron. B wrongfully refuses to receive the iron. B must pay to A, by way of compensation, the difference between the contract price of the iron and the sum for which A could have obtained and delivered it
i. A delivers to B, a common carrier, a machine, to be conveyed, without delay, to A's mill, informing B that his mill is stopped for want of machine. B unreasonably delays the delivery of the machine, and A, in consequence, loses a profitable contract with the Government. A is entitled to receive from B, by way of compensation, the average amount of profit which would have been made by the working of the mill during the time that delivery of it was delayed, but not the loss sustained through the loss of the Government contract.
j. A, having contracted with B to supply B with 1,000 tons of iron at 100 rupees a ton, to be delivered at a stated time, contracts with C for the purchase of 1,000 tons of iron at 80 rupees a ton, telling C that he does so for the purpose of performing his contract with B. C fails to perform his contract with A, who cannot procure other iron, and B, in consequence, rescinds the contract. C must pay to A 20,000 rupees, being the profit which A would have made by the performance of his contract with B.
k. A contracts with B to make and deliver to B, by a fixed day, for a specified price, a certain piece of machinery. A does not deliver the piece of machinery, at the time specified, and, in consequence of this, B is obliged to procure another at a higher price than that which he was to have paid to A, and is prevented from performing a contract which B had made with a third person at the time of his contract with A (but which had not been communicated to A),and is compelled to make compensation for breach of that contract. A must pay to B, by way of compensation, the difference between the contract price of the price of machinery and the sum paid by B for another, but not the sum paid by B to the third person by way of compensation.
l. A, a builder, contracts to erect and finish a house by the first of January, in order that B may give possession of it at that time to C, to whom B has contracted to let it. A is informed of the contract between B and C. A builds the house so badly that, before the first of January, it falls down and has to be re- built by B, who, in consequence, loses the rent which he was to have received from C, and is obliged to make compensations to C for the breach of his contract. A must make compensation to B for the cost of rebuilding of the house, for the rent lost, and for the compensation made to C.
m. A sells certain merchandise to B, warranting it to be of a particular quality, and B, in reliance upon this warranty, sells it to C with a similar warranty. The goods prove to be not according to the warranty, and B becomes liable to pay C a sum of money by way of compensation. B is entitled to be reimbursed this sum by A.
n. A contracts to pay a sum of money to B on a day specified. A does not pay the money on that day. B, in consequence of not receiving the money on that day, is unable to pay his debts, and is totally ruined. A is not liable to make good to B anything except the principal sum he contracted to pay, together with interest upto the day of payment.
O. A contracts to deliver 50 maunds of saltpetre to B on the first of January, at acertain price, B, afterwards, before the first of January, contracts to sell the saltpetre to C at a price higher than the market price of the first of January. A breaks his promise. In estimating the compensation payable by A to B, the market price of the first of January, and not the profit which would have arisen to B from the sale to C, is to be taken into account.
p. A contracts to sell and deliver 500 bales of cotton to B on a fixed day. A knows nothing of B's mode of conducting his business. A breaks his promise, and B, having no cotton, is obliged to close his mill. A is not responsible to B for the loss caused to B by closing of the mill.
q. A contracts to sell and deliver to B, on the first of January, certain cloth which B intends to manufacture into caps of a particular kind, for which there is no demand, except at that season. The cloth is not delivered till after the appointed time, and too late to be used that year in making caps. B is entitled to receive from A, by way of compensation, the difference between the contract price of the cloth and its market price at the time of delivery, but not the profits which he expected to obtain by making caps, nor the expenses which he has been put to in making preparation for the manufacture.
r. A, a ship owner, contracts with B to convey him from Calcutta to Sydney in A's ship, sailing on the first of January, and B pays to A, by way of deposit, one-half of his passage-money. The ship does not sail on the first of January, and B, after being, in consequence, detained in Calcutta for some time, and thereby put to some expense, proceeds to Sydney in another vessel, and, in consequence, arriving too late in Sydney, loses a sum of money. A is liable to repay to B his deposit, with interest, and the expense to which he is put by his detention in Calcutta, and the excess, if any, of the passage-money paid for the second ship over that agreed upon for the first, but not the sum of money which B lost by arriving in Sydney too late.
73. Compensation for breach of contract where penalty stipulated for.—
When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for.
Explanation.— A stipulation for increased interest from the date of default may be a stipulation by way of penalty.
Exception.—
When any person enters into any bail-bond, recognizance or other instrument of the same nature or, under the provisions of any law, or under the orders of the Central Government or of any State Government, gives any bond for the performance of any public duty or act in which the public are interested, he shall be liable, upon breach of the condition of any such instrument, to pay the whole sum mentioned therein.
Explanation.—A person who enters into a contract with Government does not necessarily thereby undertake any public duty, or promise to do an act in which the public are interested.
Illustrations
a. A contracts with B to pay B Rs, 1,000 if he fails to pay B Rs. 500 on a given day. A fails to pay B Rs. 500 on that day. B is entitled to recover from A such compensation, not exceeding Rs. 1,000, as the Court considers reasonable.
b. A contracts with B that, if A practises as a surgeon within Calcutta, he will pay B Rs. 5,000. Apractises as a surgeon in Calcutta. B is entitled to such compensation; not exceeding Rs. 5,000 as the court considers reasonable.
c. A gives a recognizance binding him in a penalty of Rs. 500 to appear in Court on a certain day. He forfeits his recognizance. He is liable to pay the whole penalty.
d. A gives B a bond for the repayment of Rs. 1,000 with interest at 12 per cent, at the end of six months, with a stipulation that, in case of default, interest shall be payable at the rate of 75 per cent, from the date of default. This is a stipulation by way of penalty, and B is only entitled to recover from A such compensation as the Court considers reasonable.
e. A, who owes money to B, a money-lender, undertakes to repay him by delivering to him 10 maunds of grain on a certain date, and stipulates that, in the event of his not delivering the stipulated amount by the stipulated date, he shall be liable to deliver 20 maunds. This is a stipulation by way of penalty, and B is only entitled to reasonable consideration in case of breach.
f. A undertakes to repay B a loan of Rs. 1,000 by five equal monthly installments, with a stipulation that, in default, of payment of any installment, the whole shall become due. This stipulation is not by way of penalty, and the contract may be enforced according to its terms. g. A borrows Rs. 100 from B and gives him a bond for Rs. 200 payable by five yearly installments of Rs. 40, with a stipulation that, in default of payment of any installment, the whole shall become due. This is a stipulation by way of penalty.
74. Party rightfully rescinding contract, entitled to compensation.— A person who rightfully rescinds a contract is entitled to compensation for any damage which he has sustained through the non-fulfilment of the contract.
Illustration
A, a singer, contracts with B, the manager of a theatre, to sing at his theatre for two nights in every week during the next two months, and B engages to pay her 100 rupees for each night's performance On the sixth night, A willfully absents herself from the theatre, and 8, in consequence, rescinds the contracts. B is entitled to claim compensation for the damage which he has sustained through fulfilment of the contract.